Mellock Hill Wind Farm II (35 MW)

Mellock Hill Wind Farm II is a 35 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 15 May 2006; the record was last updated on 15 May 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWwind farm
application withdrawnstatus in REPD
15 May 2006record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
29 August 2005Application submitted
15 May 2006Application withdrawn

Project details

Technology
wind farm
Capacity
35 MW
Status (REPD)
application withdrawn
Record last updated
15 May 2006
Operator or applicant
Renewable Development Company Ltd
Planning authority
Perth and Kinross
Planning application reference
not recorded
Turbines
14
Address (REPD)
Ochill Hills, nr. Crook of Devon Perthshire
Council area (by location)
Perth and Kinross
REPD reference
3562

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mellock Hill Wind Farmwind farm48refused<0.1
Earnieside Farmhouse, Dunning Glen Wind Farmwind farm48approved, not built2.4
Little Law Wind Farmwind farm27refused on appeal3.6
Snowgoat Glen Wind Farmwind farm23.5application withdrawn4.5
Snowgoat Glen Wind Farm IIwind farm13refused4.5
Green knowes Windfarm Ext.wind farm10application withdrawn4.5
Green Knoweswind farm27operational5.7
Knowes Farmwind farm7.7refused7.2
Shire-End Farmsolar farm17approved, not built7.7