Earnieside Farmhouse, Dunning Glen Wind Farm (48 MW)
Earnieside Farmhouse, Dunning Glen Wind Farm is a 48 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 November 2025, not yet built; the record was last updated on 2 December 2025.
48 MWwind farm
approved, not builtstatus in REPD
2 December 2025record last updated
Perth and Kinrosscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 19 August 2024 | Application submitted |
| 7 November 2025 | Planning permission granted |
| 7 November 2025 | Appeal allowed |
Project details
- Technology
- wind farm
- Capacity
- 48 MW
- Status (REPD)
- approved, not built
- Record last updated
- 2 December 2025
- Operator or applicant
- Galileo Green Energy Scotland Limited
- Planning authority
- Perth and Kinross
- Planning application reference
- 24/01193/FLM
- Turbines
- 8
- Address (REPD)
- 1.5km, Ne/O Earnieside Farmhouse, Dunning Glen, Dollar
- Council area (by location)
- Perth and Kinross
- Time to decision
- 64 weeks
- Name in REPD
- Earnieside Farmhouse, Dunning Glen - Wind Farm
- REPD reference
- 15299
Who decides
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Mellock Hill Wind Farm II | wind farm | 35 | application withdrawn | 2.4 |
| Mellock Hill Wind Farm | wind farm | 48 | refused | 2.4 |
| Green knowes Windfarm Ext. | wind farm | 10 | application withdrawn | 3.4 |
| Little Law Wind Farm | wind farm | 27 | refused on appeal | 4.4 |
| Green Knowes | wind farm | 27 | operational | 4.9 |
| Snowgoat Glen Wind Farm II | wind farm | 13 | refused | 5.7 |
| Snowgoat Glen Wind Farm | wind farm | 23.5 | application withdrawn | 5.7 |
| Frandy Hill | wind farm | 14 | refused on appeal | 8.5 |
| Balado Windfarm | wind farm | 5.6 | refused | 8.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2252, -3.6001).