Energy Projects Near You

Earnieside Farmhouse, Dunning Glen Wind Farm (48 MW)

Earnieside Farmhouse, Dunning Glen Wind Farm is a 48 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 November 2025, not yet built; the record was last updated on 2 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
approved, not builtstatus in REPD
2 December 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
19 August 2024Application submitted
7 November 2025Planning permission granted
7 November 2025Appeal allowed

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
approved, not built
Record last updated
2 December 2025
Operator or applicant
Galileo Green Energy Scotland Limited
Planning authority
Perth and Kinross
Planning application reference
24/01193/FLM
Turbines
8
Address (REPD)
1.5km, Ne/O Earnieside Farmhouse, Dunning Glen, Dollar
Council area (by location)
Perth and Kinross
Time to decision
64 weeks
Name in REPD
Earnieside Farmhouse, Dunning Glen - Wind Farm
REPD reference
15299

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mellock Hill Wind Farm IIwind farm35application withdrawn2.4
Mellock Hill Wind Farmwind farm48refused2.4
Green knowes Windfarm Ext.wind farm10application withdrawn3.4
Little Law Wind Farmwind farm27refused on appeal4.4
Green Knoweswind farm27operational4.9
Snowgoat Glen Wind Farm IIwind farm13refused5.7
Snowgoat Glen Wind Farmwind farm23.5application withdrawn5.7
Frandy Hillwind farm14refused on appeal8.5
Balado Windfarmwind farm5.6refused8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2252, -3.6001).