Frandy Hill (14 MW wind farm)
Frandy Hill is a 14 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 11 April 2013; the record was last updated on 21 November 2013.
14 MWwind farm
refused on appealstatus in REPD
21 November 2013record last updated
Perth and Kinrosscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 9 December 2011 | Application submitted |
| 11 April 2013 | Refused by the planning authority |
| 11 April 2013 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 14 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 21 November 2013
- Operator or applicant
- Wind Prospect Developments
- Planning authority
- Perth and Kinross
- Planning application reference
- 11/01952/FLL
- Appeal reference
- 13/00004/NONDET
- Turbines
- 7
- Address (REPD)
- Site South Of The Upper And Lower Glendevon Resevoirs Glendevon
- Council area (by location)
- Perth and Kinross
- Time to decision
- 70 weeks
- REPD reference
- 3913
Who decides
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Burnfoot East Wind Farm (further extension) | wind farm | 10.8 | operational | 1.6 |
| Burnfoot Hill | wind farm | 26 | operational | 2.4 |
| Rhodders Wind Farm | wind farm | 12 | operational | 3.1 |
| Rowan Gate Solar Farm | solar farm | 7 | approved, not built | 5.2 |
| Green Knowes | wind farm | 27 | operational | 5.9 |
| Green knowes Windfarm Ext. | wind farm | 10 | application withdrawn | 6.3 |
| Windburn Wind Farm | wind farm | 65 | application submitted | 7.6 |
| Balhearty Solar | solar farm | 5 | operational | 7.8 |
| Bankhead Farm | battery storage | 25 | approved, not built | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2119, -3.7348).