Frandy Hill (14 MW wind farm)

Frandy Hill is a 14 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 11 April 2013; the record was last updated on 21 November 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWwind farm
refused on appealstatus in REPD
21 November 2013record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
9 December 2011Application submitted
11 April 2013Refused by the planning authority
11 April 2013Appeal refused

Project details

Technology
wind farm
Capacity
14 MW
Status (REPD)
refused on appeal
Record last updated
21 November 2013
Operator or applicant
Wind Prospect Developments
Planning authority
Perth and Kinross
Planning application reference
11/01952/FLL
Appeal reference
13/00004/NONDET
Turbines
7
Address (REPD)
Site South Of The Upper And Lower Glendevon Resevoirs Glendevon
Council area (by location)
Perth and Kinross
Time to decision
70 weeks
REPD reference
3913

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burnfoot East Wind Farm (further extension)wind farm10.8operational1.6
Burnfoot Hillwind farm26operational2.4
Rhodders Wind Farmwind farm12operational3.1
Rowan Gate Solar Farmsolar farm7approved, not built5.2
Green Knoweswind farm27operational5.9
Green knowes Windfarm Ext.wind farm10application withdrawn6.3
Windburn Wind Farmwind farm65application submitted7.6
Balhearty Solarsolar farm5operational7.8
Bankhead Farmbattery storage25approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2119, -3.7348).