Rhodders Wind Farm (12 MW)
Rhodders Wind Farm is a 12 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 February 2016; the record was last updated on 29 February 2016.
12 MWwind farm
operationalstatus in REPD
29 February 2016record last updated
Perth and Kinrosscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 7 November 2011 | Application submitted |
| 8 July 2013 | Refused by the planning authority |
| 21 January 2014 | Planning permission granted |
| 21 January 2014 | Appeal allowed |
| 1 August 2015 | Construction started |
| 29 February 2016 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- operational
- Record last updated
- 29 February 2016
- Operator or applicant
- EDF/Wind Prospect
- Planning authority
- Clackmannanshire
- Planning application reference
- 11/00299/FULL
- Appeal reference
- 13/00001/REFUSE
- Turbines
- 6
- Address (REPD)
- Site West Of Burnfoot Hill Tillicoultry Clackmannanshire
- Council area (by location)
- Perth and Kinross
- Time to decision
- 115 weeks
- REPD reference
- 4223
Who decides
Clackmannanshire has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Burnfoot Hill | wind farm | 26 | operational | 0.8 |
| Burnfoot East Wind Farm (further extension) | wind farm | 10.8 | operational | 1.5 |
| Frandy Hill | wind farm | 14 | refused on appeal | 3.1 |
| Rowan Gate Solar Farm | solar farm | 7 | approved, not built | 5.9 |
| Windburn Wind Farm | wind farm | 65 | application submitted | 6.0 |
| Bankhead Farm | battery storage | 25 | approved, not built | 6.9 |
| Balhearty Solar | solar farm | 5 | operational | 8.1 |
| Devilla Energy Storage Facility | battery storage | 500 | under construction | 8.1 |
| Green Knowes | wind farm | 27 | operational | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2042, -3.7824).