Balhearty Solar (5 MW)

Balhearty Solar is a 5 MW solar farm project in Clackmannanshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 5 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
5 July 2018record last updated
Clackmannanshirecouncil area

Planning timeline

DateStage
20 October 2015Application submitted
23 December 2015Planning permission granted
1 February 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
5 July 2018
Operator or applicant
NESF (formerly Lark Energy)
Planning authority
Clackmannanshire
Planning application reference
15/00188/FULL
Site area
12.0 ha
Address (REPD)
Balhearty, Coalsnaughton, Tillicoultry
Council area (by location)
Clackmannanshire
Time to decision
9 weeks
REPD reference
5795

Who decides

Clackmannanshire has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bankhead Farmbattery storage25approved, not built4.0
Devilla Energy Storage Facilitybattery storage500under construction4.6
Windburn Wind Farmwind farm65application submitted4.7
Easter Muirhead Farmwind farm15refused5.2
Forthbankwind farm5refused6.4
Muirmealing Solar Farmsolar farm5abandoned6.8
Kincardine Battery Storagebattery storage342approved, not built7.2
West Grange Solar Farmsolar farm5abandoned7.5
Frandy Hillwind farm14refused on appeal7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.143, -3.712).