Easter Muirhead Farm (15 MW wind farm)

Easter Muirhead Farm is a 15 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 October 2018; the record was last updated on 8 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refusedstatus in REPD
8 October 2013record last updated
Fifecouncil area

Planning timeline

DateStage
12 June 2009Application submitted
19 October 2018Refused by the planning authority

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused
Record last updated
8 October 2013
Operator or applicant
ABO Wind UK
Planning authority
Fife
Planning application reference
09/01359/WEIA
Turbines
5
Address (REPD)
North of Saline, Dunfermline, Fife
Council area (by location)
Fife
Time to decision
488 weeks
REPD reference
2699

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Muirmealing Solar Farmsolar farm5abandoned1.7
West Grange Solar Farmsolar farm5abandoned4.2
Balhearty Solarsolar farm5operational5.2
Nettly Burn Renewable Energy Parksolar farm80approved, not built7.6
Outh Muir Wind Farmwind farm12.5refused on appeal8.3
Kincardine Grid Services Complex Energy Storage Facilitybattery storage400approved, not built8.3
Kincardine Battery Storagebattery storage342approved, not built8.4
Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm40approved, not built8.7
Bankhead Farmbattery storage25approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1281, -3.6318).