Kincardine Grid Services Complex Energy Storage Facility (400 MW)

Kincardine Grid Services Complex Energy Storage Facility is a 400 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 January 2022, not yet built; the record was last updated on 8 June 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. REPD also records that the planning permission expired on 5 January 2023, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtmay be out of datestatus in REPD
8 June 2022record last updated
Fifecouncil area

REPD also records that the planning permission expired on 5 January 2023, so the project may not go ahead in this form.

Planning timeline

DateStage
19 August 2021Application submitted
5 January 2022Section 36 consent granted (Scottish Ministers)
5 January 2023Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
8 June 2022
Operator or applicant
Amp Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003326
Address (REPD)
N/O Kincardine Substation, Kincardine, Alloa
Council area (by location)
Fife
Time to decision
20 weeks
Name in REPD
Kincardine Grid Services Complex - Energy Storage Facility
REPD reference
10536

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kincardine Battery Storagebattery storage342approved, not built1.0
Forthbankwind farm5refused4.3
West Grange Solar Farmsolar farm5abandoned5.8
Devilla Energy Storage Facilitybattery storage500under construction7.5
Merchiston Industrial Estate, Smith Streetbattery storage43under construction7.5
Balhearty Solarsolar farm5operational7.8
Land To The East Of Wholeflats Road (Grangemouth)battery storage20permission expired8.2
Easter Muirhead Farmwind farm15refused8.3
Bankhead Farmbattery storage25approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0729, -3.7231).