Merchiston Industrial Estate, Smith Street (43 MW battery storage)

Merchiston Industrial Estate, Smith Street is a 43 MW battery storage project in Falkirk, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 November 2025; the record was last updated on 2 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43 MWbattery storage
under constructionstatus in REPD
2 December 2025record last updated
Falkirkcouncil area

Planning timeline

DateStage
7 February 2023Application submitted
23 June 2023Planning permission granted
1 November 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
43 MW
Status (REPD)
under construction
Record last updated
2 December 2025
Operator or applicant
Falkirk Power Limited
Planning authority
Falkirk
Planning application reference
P/23/0046/FUL
Address (REPD)
The South East Of Merchiston Industrial Estate Smith Street
Council area (by location)
Falkirk
Time to decision
19 weeks
Name in REPD
Merchiston Industrial Estate, Smith Street - Battery Storage
REPD reference
13225

Who decides

ApplicationsFalkirkUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused0 of 812%
Onshore wind refused3 of 545%
Battery storage refused0 of 616%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land adjacent Bonnybridge Substationbattery storage19.9abandoned4.7
Land To The East Of Wholeflats Road (Grangemouth)battery storage20permission expired5.2
Tod Hill Farm Wind Turbineswind farm12operational5.4
Glenside Farmbattery storage400approved, not built7.4
Kincardine Grid Services Complex Energy Storage Facilitybattery storage400approved, not built7.5
Kincardine Battery Storagebattery storage342approved, not built7.9
Forthbankwind farm5refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0137, -3.7823).