Energy Projects Near You

Land To The East Of Wholeflats Road (Grangemouth) (20 MW battery storage)

Land To The East Of Wholeflats Road (Grangemouth) is a 20 MW battery storage project in Falkirk, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 17 July 2021; the record was last updated on 12 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
permission expiredstatus in REPD
12 August 2020record last updated
Falkirkcouncil area

Planning timeline

DateStage
11 April 2018Application submitted
17 July 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
permission expired
Record last updated
12 August 2020
Operator or applicant
Enstor (formerly CJ Energy)
Planning authority
Falkirk
Planning application reference
P/18/0201/FUL
Address (REPD)
Unit 2, Land To The East Of, Wholeflats Road, Grangemouth, Central
Council area (by location)
Falkirk
REPD reference
7043

Who decides

ApplicationsFalkirkUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused0 of 812%
Onshore wind refused3 of 545%
Battery storage refused0 of 616%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Merchiston Industrial Estate, Smith Streetbattery storage43under construction5.2
Kincardine Grid Services Complex Energy Storage Facilitybattery storage400approved, not built8.2
Kincardine Battery Storagebattery storage342approved, not built9.0
Land adjacent Bonnybridge Substationbattery storage19.9abandoned9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0005, -3.7017).