Energy Projects Near You

Glenside Farm (400 MW battery storage)

Glenside Farm is a 400 MW battery storage project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 February 2025, not yet built; the record was last updated on 10 March 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
10 March 2025record last updated
Stirlingcouncil area

Planning timeline

DateStage
9 February 2024Application submitted
25 February 2025Section 36 consent granted (Scottish Ministers)
25 February 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
10 March 2025
Operator or applicant
Apatura
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005047
Address (REPD)
Glenside Farm, Plean
Council area (by location)
Stirling
Time to decision
55 weeks
Name in REPD
Glenside Farm - Battery Storage
REPD reference
14988

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tod Hill Farm Wind Turbineswind farm12operational2.4
Land adjacent Bonnybridge Substationbattery storage19.9abandoned4.9
Rullie Community Windfarmwind farm25application withdrawn5.1
Shelloch Wind Farmwind farm24approved, not built5.5
Earlsburn Wind Farm Extensionwind farm34approved, not built6.5
Farm at Lower Polmaisesolar farm5permission expired7.3
Merchiston Industrial Estate, Smith Streetbattery storage43under construction7.4
Unit 15, Borrowmeadow Roadbattery storage19abandoned7.6
Easter Cringate Cottage, Polmaise Roadwind farm30application submitted8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0516, -3.8805).