Easter Cringate Cottage, Polmaise Road (30 MW wind farm)

Easter Cringate Cottage, Polmaise Road is a 30 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 6 August 2024, no decision recorded; the record was last updated on 10 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
application submittedstatus in REPD
10 September 2024record last updated
Stirlingcouncil area

Planning timeline

DateStage
6 August 2024Application submitted

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
application submitted
Record last updated
10 September 2024
Operator or applicant
Drummarnock Wind Farm Limited
Planning authority
Stirling
Planning application reference
24/00494/FUL
Turbines
4
Turbine height
180 m
Address (REPD)
1340M South East Of Easter Cringate Cottage Polmaise Road Fintry
Council area (by location)
Stirling
Name in REPD
Easter Cringate Cottage, Polmaise Road - Wind Turbines
REPD reference
16991

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Unit 15, Borrowmeadow Roadbattery storage19abandoned1.4
Earlsburn Wind Farm Extensionwind farm34approved, not built2.3
Shelloch Wind Farmwind farm24approved, not built2.6
Manor Powissolar farm5application withdrawn3.4
Farm at Lower Polmaisesolar farm5permission expired3.7
Muirparkwind farm33refused8.1
Glenside Farmbattery storage400approved, not built8.2
Rullie Community Windfarmwind farm25application withdrawn8.5
Devilla Energy Storage Facilitybattery storage500under construction9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1182, -3.9362).