Farm at Lower Polmaise (5 MW solar farm)

Farm at Lower Polmaise is a 5 MW solar farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 8 October 2018; the record was last updated on 23 October 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
23 October 2019record last updated
Stirlingcouncil area

Planning timeline

DateStage
3 September 2015Application submitted
8 October 2015Planning permission granted
8 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
23 October 2019
Operator or applicant
Stirling Council
Planning authority
Stirling
Planning application reference
15/00492/FUL
Site area
19.8 ha
Address (REPD)
485M South East of, Lower Polmaise Refuse Handling, Fallin, Stirling, Central, Scotland
Council area (by location)
Stirling
Time to decision
5 weeks
REPD reference
5911

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Powissolar farm5application withdrawn2.1
Unit 15, Borrowmeadow Roadbattery storage19abandoned2.3
Shelloch Wind Farmwind farm24approved, not built3.4
Easter Cringate Cottage, Polmaise Roadwind farm30application submitted3.7
Earlsburn Wind Farm Extensionwind farm34approved, not built4.7
Devilla Energy Storage Facilitybattery storage500under construction6.0
Forthbankwind farm5refused6.5
Windburn Wind Farmwind farm65application submitted6.7
Bankhead Farmbattery storage25approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1169, -3.8763).