Bankhead Farm (25 MW battery storage)

Bankhead Farm is a 25 MW battery storage project in Clackmannanshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 May 2024, not yet built; the record was last updated on 13 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtstatus in REPD
13 May 2024record last updated
Clackmannanshirecouncil area

Planning timeline

DateStage
16 January 2024Application submitted
2 May 2024Planning permission granted
2 May 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
13 May 2024
Operator or applicant
Low Carbon Storage
Planning authority
Clackmannanshire
Planning application reference
24/00001/FULL
Address (REPD)
Bankhead Farm, Fishcross, Alloa
Council area (by location)
Clackmannanshire
Time to decision
15 weeks
Name in REPD
Bankhead Farm - Energy Storage System
REPD reference
14450

Who decides

Clackmannanshire has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Windburn Wind Farmwind farm65application submitted1.1
Devilla Energy Storage Facilitybattery storage500under construction1.3
Balhearty Solarsolar farm5operational4.0
Forthbankwind farm5refused5.0
Farm at Lower Polmaisesolar farm5permission expired6.8
Rhodders Wind Farmwind farm12operational6.9
Manor Powissolar farm5application withdrawn7.1
Burnfoot Hillwind farm26operational7.4
Kincardine Battery Storagebattery storage342approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1423, -3.7764).