Solar, wind and battery projects near Stirling (FK7)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FK7 (Stirling): 1 is waiting for a planning decision, 14 approved but not yet running, 3 operational. The largest live scheme is Devilla Energy Storage Facility (500 MW battery storage, under construction since 1 March 2025), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of FK7
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Shelloch Wind Farmwind farm | wind farm | 24 | approved, not builtupdated Aug 2025 | Jan 2021 | granted Feb 2022 | Aug 2025 | Stirling | 0.1 |
| Earlsburn Wind Farm Extensionwind farm | wind farm | 34 | approved, not builtupdated Jan 2026 | Dec 2022 | granted Dec 2025 | Jan 2026 | Stirling | 1.7 |
| Earlsburn Wind Farm Extensionbattery storage | battery storage | 18 | approved, not builtupdated Jan 2026 | Dec 2022 | granted Dec 2025 | Jan 2026 | Stirling | 1.7 |
| Pirnhall Services, Bannockburn Interchangesolar farm | solar farm | 4 | approved, not builtupdated Jul 2025 | May 2024 | granted May 2025 | Jul 2025 | Stirling | 2.3 |
| Unit 15, Borrowmeadow Roadbattery storage | battery storage | 19 | abandonedupdated Nov 2019 | Aug 2017 | — | Nov 2019 | Stirling | 2.4 |
| Forthside Way Battery Storage Unitbattery storage | battery storage | 1 | approved, not built may be out of dateupdated Jan 2022 | Nov 2021 | granted Dec 2021 | Jan 2022 | Stirling | 2.5 |
| Easter Cringate Cottage, Polmaise Roadwind farm | wind farm | 30 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Stirling | 2.7 |
| Farm at Lower Polmaisesolar farm | solar farm | 5 | permission expiredupdated Oct 2019 | Sep 2015 | granted Oct 2015 | Oct 2019 | Stirling | 3.5 |
| Manor Powissolar farm | solar farm | 5 | application withdrawnupdated Jul 2017 | Jul 2016 | — | Jul 2017 | Stirling | 4.6 |
| Glenside Farmbattery storage | battery storage | 400 | approved, not builtupdated Mar 2025 | Feb 2024 | granted Feb 2025 | Mar 2025 | Stirling | 5.5 |
| Rullie Community Windfarmwind farm | wind farm | 25 | application withdrawnupdated Oct 2012 | Dec 2011 | — | Oct 2012 | Falkirk | 6.5 |
| Rosehill Wind Turbineswind farm | wind farm | 2.4 | operationalupdated Feb 2016 | Oct 2012 | granted Apr 2014 | Feb 2016 | Stirling | 7.2 |
| Muirparkwind farm | wind farm | 33 | refusedupdated May 2012 | Mar 2009 | refused May 2012 | May 2012 | Stirling | 7.5 |
| Tod Hill Farm Wind Turbineswind farm | wind farm | 12 | operationalupdated May 2015 | Jun 2011 | granted Jun 2012 | May 2015 | Falkirk | 7.9 |
| Forthbankwind farm | wind farm | 5 | refusedupdated Nov 2012 | Nov 2010 | refused Oct 2012 | Nov 2012 | Falkirk | 8.8 |
| Devilla Energy Storage Facilitybattery storage | battery storage | 500 | under constructionupdated Oct 2025 | Apr 2022 | granted Dec 2023 | Oct 2025 | Clackmannanshire | 9.2 |
| Craigengeltwind farm | wind farm | 20 | operationalupdated Jun 2010 | Dec 2006 | granted Feb 2008 | Jun 2010 | Stirling | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Airthrey Road PV Solar Panelsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2022 | Dec 2021 | granted Feb 2022 | Feb 2022 | Stirling | 5.0 |
| Cottrell Building, East Link Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2024 | Jun 2024 | granted Aug 2024 | Sep 2024 | Stirling | 5.5 |
| University Of Stirling, Airthrey Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | Stirling | 5.9 |
| Alloa Wastewater Treatment Works, Bowhouse Roadsolar farm | solar farm | 0.9 | approved, not built may be out of dateupdated Jul 2023 | Mar 2023 | granted Jul 2023 | Jul 2023 | Clackmannanshire | 7.9 |
| Denny Wastewater Treatment, Winchester Avenuesolar farm | solar farm | 0.4 | approved, not builtupdated Dec 2022 | Aug 2022 | granted Nov 2022 | Dec 2022 | Falkirk | 8.0 |
| North Inches Solar Photovoltaic Electricity Generationsolar farm | solar farm | — | application withdrawnupdated Nov 2023 | Mar 2022 | — | Nov 2023 | Falkirk | 8.1 |
| Central Boulevard, Central Parkrooftop solar | rooftop solar | — | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Falkirk | 8.6 |
| Forth Valley Royal Hospital, Stirling Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jul 2023 | granted Aug 2023 | Aug 2023 | Falkirk | 8.9 |
Distance from the average position of the FK7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 0 | 3 | 0 | 0 | 5.4 |
| Rooftop solar | 5 | 0 | 5 | 0 | 0 | 1 |
| Wind farm | 9 | 1 | 2 | 3 | 2 | 88 |
| Battery storage | 5 | 0 | 4 | 0 | 0 | 919 |
MW in pipeline: pending, approved and under-construction capacity.
How Stirling decides solar, wind and battery applications
| Applications | Stirling | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 7 (30%) | 19% |
| Solar refused | 0 of 7 | 12% |
| Onshore wind refused | 6 of 11 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 30.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FK7, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.