Energy Projects Near You

Solar, wind and battery projects near Stirling (FK7)

25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FK7 (Stirling): 1 is waiting for a planning decision, 14 approved but not yet running, 3 operational. The largest live scheme is Devilla Energy Storage Facility (500 MW battery storage, under construction since 1 March 2025), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25projects within 10 km
1awaiting a decision
14approved, not running
3operational

Projects within 10 km of FK7

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Shelloch Wind Farmwind farmwind farm24approved, not builtupdated Aug 2025Jan 2021granted Feb 2022Aug 2025Stirling0.1
Earlsburn Wind Farm Extensionwind farmwind farm34approved, not builtupdated Jan 2026Dec 2022granted Dec 2025Jan 2026Stirling1.7
Earlsburn Wind Farm Extensionbattery storagebattery storage18approved, not builtupdated Jan 2026Dec 2022granted Dec 2025Jan 2026Stirling1.7
Pirnhall Services, Bannockburn Interchangesolar farmsolar farm4approved, not builtupdated Jul 2025May 2024granted May 2025Jul 2025Stirling2.3
Unit 15, Borrowmeadow Roadbattery storagebattery storage19abandonedupdated Nov 2019Aug 2017—Nov 2019Stirling2.4
Forthside Way Battery Storage Unitbattery storagebattery storage1approved, not built may be out of dateupdated Jan 2022Nov 2021granted Dec 2021Jan 2022Stirling2.5
Easter Cringate Cottage, Polmaise Roadwind farmwind farm30application submittedupdated Sep 2024Aug 2024—Sep 2024Stirling2.7
Farm at Lower Polmaisesolar farmsolar farm5permission expiredupdated Oct 2019Sep 2015granted Oct 2015Oct 2019Stirling3.5
Manor Powissolar farmsolar farm5application withdrawnupdated Jul 2017Jul 2016—Jul 2017Stirling4.6
Glenside Farmbattery storagebattery storage400approved, not builtupdated Mar 2025Feb 2024granted Feb 2025Mar 2025Stirling5.5
Rullie Community Windfarmwind farmwind farm25application withdrawnupdated Oct 2012Dec 2011—Oct 2012Falkirk6.5
Rosehill Wind Turbineswind farmwind farm2.4operationalupdated Feb 2016Oct 2012granted Apr 2014Feb 2016Stirling7.2
Muirparkwind farmwind farm33refusedupdated May 2012Mar 2009refused May 2012May 2012Stirling7.5
Tod Hill Farm Wind Turbineswind farmwind farm12operationalupdated May 2015Jun 2011granted Jun 2012May 2015Falkirk7.9
Forthbankwind farmwind farm5refusedupdated Nov 2012Nov 2010refused Oct 2012Nov 2012Falkirk8.8
Devilla Energy Storage Facilitybattery storagebattery storage500under constructionupdated Oct 2025Apr 2022granted Dec 2023Oct 2025Clackmannanshire9.2
Craigengeltwind farmwind farm20operationalupdated Jun 2010Dec 2006granted Feb 2008Jun 2010Stirling9.4
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Airthrey Road PV Solar Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2022Dec 2021granted Feb 2022Feb 2022Stirling5.0
Cottrell Building, East Link Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024Stirling5.5
University Of Stirling, Airthrey Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Stirling5.9
Alloa Wastewater Treatment Works, Bowhouse Roadsolar farmsolar farm0.9approved, not built may be out of dateupdated Jul 2023Mar 2023granted Jul 2023Jul 2023Clackmannanshire7.9
Denny Wastewater Treatment, Winchester Avenuesolar farmsolar farm0.4approved, not builtupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Falkirk8.0
North Inches Solar Photovoltaic Electricity Generationsolar farmsolar farm—application withdrawnupdated Nov 2023Mar 2022—Nov 2023Falkirk8.1
Central Boulevard, Central Parkrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Falkirk8.6
Forth Valley Royal Hospital, Stirling Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Falkirk8.9

Distance from the average position of the FK7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm603005.4
Rooftop solar505001
Wind farm9123288
Battery storage50400919

MW in pipeline: pending, approved and under-construction capacity.

How Stirling decides solar, wind and battery applications

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Stirling

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FK7, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.