Energy Projects Near You

Solar, wind and battery projects near Bonnybridge (FK4)

28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FK4 (Falkirk): 2 are waiting for a planning decision, 14 approved but not yet running, 3 operational. The largest live scheme is Glenside Farm (400 MW battery storage, approved on 25 February 2025, not yet built), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28projects within 10 km
2awaiting a decision
14approved, not running
3operational

Projects within 10 km of FK4

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land adjacent Bonnybridge Substationbattery storagebattery storage19.9abandonedupdated Jul 2019Mar 2017—Jul 2019Falkirk3.5
Tod Hill Farm Wind Turbineswind farmwind farm12operationalupdated May 2015Jun 2011granted Jun 2012May 2015Falkirk4.9
Rullie Community Windfarmwind farmwind farm25application withdrawnupdated Oct 2012Dec 2011—Oct 2012Falkirk6.2
Glenside Farmbattery storagebattery storage400approved, not builtupdated Mar 2025Feb 2024granted Feb 2025Mar 2025Stirling6.4
Glenhead Farm Lower Solar Arraysolar farmsolar farm4.1permission expiredupdated Jul 2020Oct 2015granted Jul 2016Jul 2020North Lanarkshire7.0
Glenhead Farm (Upper)solar farmsolar farm5permission expiredupdated Jul 2020Oct 2015granted Jul 2016Jul 2020North Lanarkshire7.3
Greenhill Farmwind turbinewind turbine2application withdrawnupdated Oct 2017Jun 2017—Oct 2017Falkirk7.9
Berryhill Farm Solar Arraysolar farmsolar farm4.8permission expiredupdated Jul 2020Oct 2015granted Jul 2016Jul 2020North Lanarkshire7.9
Merchiston Industrial Estate, Smith Streetbattery storagebattery storage43under constructionupdated Dec 2025Feb 2023granted Jun 2023Dec 2025Falkirk8.0
Rosehill Wind Turbineswind farmwind farm2.4operationalupdated Feb 2016Oct 2012granted Apr 2014Feb 2016Stirling8.2
Glenhove Pumping Station, Glenhove Roadbattery storagebattery storage3.1application submittedMay 2026——North Lanarkshire8.3
Glenhove Pumping Station, Glenhove Roadsolar farmsolar farm1.9application submittedMay 2026——North Lanarkshire8.3
Pirnhall Services, Bannockburn Interchangesolar farmsolar farm4approved, not builtupdated Jul 2025May 2024granted May 2025Jul 2025Stirling8.9
ASDA Distribution Centrewind turbinewind turbine2permission expiredupdated Apr 2017Nov 2007granted Mar 2009Apr 2017Falkirk8.9
Asda Grangemouth Depotwind farmwind farm4refusedupdated Mar 2009Feb 2007refused Dec 2007Mar 2009Falkirk9.4
Greendykesidewind farmwind farm4operationalupdated Oct 2009Sep 2004granted May 2005Oct 2009North Lanarkshire9.4
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Roughmute Sewage Treatment Worksrooftop solarrooftop solar0.8approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Falkirk2.8
Denny Wastewater Treatment, Winchester Avenuesolar farmsolar farm0.4approved, not builtupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Falkirk3.2
Forth Valley Royal Hospital, Stirling Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Falkirk4.9
Central Boulevard, Central Park - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Falkirk5.1
Unit 2, Tamfourhill Avenue - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Falkirk5.1
Central Boulevard, Central Parkrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Falkirk6.1
West Carron Works, Stenhouse Roadrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Falkirk7.1
North Inches Solar Photovoltaic Electricity Generationsolar farmsolar farm—application withdrawnupdated Nov 2023Mar 2022—Nov 2023Falkirk7.2
Wonder World, Castlelaurie Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Falkirk8.1
Greens Road, Blairlinnrooftop solarrooftop solar0.4approved, not builtupdated May 2024Apr 2024granted May 2024May 2024North Lanarkshire8.8
Abbotshaugh, Sawmill Abbots Roadbattery storagebattery storage—approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Falkirk9.3
The Helix Park - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Falkirk9.5

Distance from the average position of the FK4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm712006.3
Rooftop solar606002.2
Wind farm500310
Wind turbine200000
Battery storage81600447

MW in pipeline: pending, approved and under-construction capacity.

How Falkirk decides solar, wind and battery applications

ApplicationsFalkirkUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused0 of 812%
Onshore wind refused3 of 545%
Battery storage refused0 of 616%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Falkirk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FK4, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.