Nettly Burn Renewable Energy Park (80 MW)

Nettly Burn Renewable Energy Park is an 80 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 March 2026, not yet built; the record was last updated on 22 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

80 MWsolar farm
approved, not builtstatus in REPD
22 June 2026record last updated
Fifecouncil area

Planning timeline

DateStage
22 October 2024Application submitted
6 March 2026Section 36 consent granted (Scottish Ministers)
6 March 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
80 MW
Status (REPD)
approved, not built
Record last updated
22 June 2026
Operator or applicant
Grupotec Solar UK 4 Ltd
Planning authority
Scottish Government (S36)
Planning application reference
ECU00006007
Site area
127.0 ha
Address (REPD)
Knockhill Racing Circuit, Dunfermline
Council area (by location)
Fife
Time to decision
71 weeks
REPD reference
15538

The scheme also includes 15 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Outh Muir Wind Farmwind farm12.5refused on appeal0.9
Blairadam Wind Farmwind farm22.6refused2.8
Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm40approved, not built3.8
Dunfermline North Solar Photovoltaic Array/Battery storagesolar farm29.9under construction4.5
Muirmealing Solar Farmsolar farm5abandoned6.6
Easter Muirhead Farmwind farm15refused7.6
Kingdom of Fife Community Wind Parkwind farm12refused8.4
Balado Windfarmwind farm5.6refused8.9
West Grange Solar Farmsolar farm5abandoned9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1314, -3.509).