Kingdom of Fife Community Wind Park (12 MW)
Kingdom of Fife Community Wind Park is a 12 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 October 2013; the record was last updated on 25 October 2013.
12 MWwind farm
refusedstatus in REPD
25 October 2013record last updated
Fifecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 25 July 2011 | Application submitted |
| 1 October 2013 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- refused
- Record last updated
- 25 October 2013
- Operator or applicant
- Atmos Consulting Ltd
- Planning authority
- Fife
- Planning application reference
- 11/03990/EIA
- Turbines
- 4
- Address (REPD)
- Land To North Of Halbeath Roundabout, Fife
- Council area (by location)
- Fife
- Time to decision
- 114 weeks
- REPD reference
- 3816
Who decides
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Cuttlehill Farm, Crossgates | battery storage | 25 | abandoned | 2.4 |
| Parkend Crossgates Solar Panels & Battery Storage | solar farm | 30 | approved, not built | 4.0 |
| Dunfermline North Solar Photovoltaic Array/Battery storage | solar farm | 29.9 | under construction | 4.3 |
| South Pargillis | battery storage | 42 | approved, not built | 4.6 |
| Mossmorran Wind Farm | wind farm | 6 | application withdrawn | 4.9 |
| STOR Field 9 | battery storage | 37 | approved, not built | 5.6 |
| Blairadam Wind Farm | wind farm | 22.6 | refused | 6.5 |
| Craigluscar, Craigluscar Road Solar Array & Battery Storage | solar farm | 40 | approved, not built | 6.7 |
| Babcock Marine Bldg, Wood Road | solar farm | 5.6 | approved, not built | 7.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0896, -3.3968).