Kinnon Park Farm, Methven Solar Farm & Battery Storage (49.9 MW)

Kinnon Park Farm, Methven Solar Farm & Battery Storage is a 49.9 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 May 2026; the record was last updated on 15 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
15 June 2026record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
10 September 2024Application submitted
13 May 2026Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
15 June 2026
Operator or applicant
Namene Solar
Planning authority
Perth and Kinross
Planning application reference
24/01188/FLM
Site area
102.1 ha
Address (REPD)
Kinnon Park Farm, Methven, Perth
Council area (by location)
Perth and Kinross
Time to decision
87 weeks
Name in REPD
Kinnon Park Farm, Methven - Solar Farm & Battery Storage
REPD reference
14664

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Taigh An Struith, Tibbermorebattery storage49.9refused1.7
Solar Array at Dupplin Solar 750 Metres S/O Newbigging Farm Tibbermoresolar farm97.5application submitted2.8
Newhouse Farm Energy Storage Facilitybattery storage49.9approved, not built3.4
Old Gallows Roadbattery storage49.9approved, not built3.7
Brunt Hill Wind Farm & Battery Storagewind farm130application submitted3.7
Parks of Kellour Wind Farmwind farm12refused6.8
Logiealmondwind farm28application withdrawn8.3
Binn Farm Solar Farmsolar farm39application submitted9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4101, -3.5458).