Taigh An Struith, Tibbermore (49.9 MW battery storage)

Taigh An Struith, Tibbermore is a 49.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 March 2025; the record was last updated on 18 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
refusedstatus in REPD
18 March 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
13 June 2024Application submitted
12 March 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
18 March 2025
Operator or applicant
Ylem Energy Limited
Planning authority
Perth and Kinross
Planning application reference
24/00750/FLM
Address (REPD)
256 Metres Sw/O Taigh An Struith, Tibbermore, Perth
Council area (by location)
Perth and Kinross
Time to decision
39 weeks
Name in REPD
Taigh An Struith, Tibbermore - Battery Energy Storage
REPD reference
15754

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kinnon Park Farm, Methven Solar Farm & Battery Storagesolar farm49.9refused1.7
Solar Array at Dupplin Solar 750 Metres S/O Newbigging Farm Tibbermoresolar farm97.5application submitted2.1
Newhouse Farm Energy Storage Facilitybattery storage49.9approved, not built2.3
Old Gallows Roadbattery storage49.9approved, not built2.3
Brunt Hill Wind Farm & Battery Storagewind farm130application submitted2.3
Binn Farm Solar Farmsolar farm39application submitted7.7
Parks of Kellour Wind Farmwind farm12refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.398, -3.5279).