Newhouse Farm Energy Storage Facility (49.9 MW)

Newhouse Farm Energy Storage Facility is a 49.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 January 2023, not yet built; the record was last updated on 29 July 2022. REPD also records that the planning permission expired on 27 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
29 July 2022record last updated
Perth and Kinrosscouncil area

REPD also records that the planning permission expired on 27 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
2 July 2022Application submitted
27 January 2023Planning permission granted
27 January 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 July 2022
Operator or applicant
Intelligent Land Investments Group
Planning authority
Perth and Kinross
Planning application reference
22/01071/FLM
Address (REPD)
170 Metres S/O Newhouse Farm, Perth
Council area (by location)
Perth and Kinross
Time to decision
30 weeks
Name in REPD
Newhouse Farm - Energy Storage Facility
REPD reference
9047

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brunt Hill Wind Farm & Battery Storagewind farm130application submitted0.6
Old Gallows Roadbattery storage49.9approved, not built0.6
Taigh An Struith, Tibbermorebattery storage49.9refused2.3
Kinnon Park Farm, Methven Solar Farm & Battery Storagesolar farm49.9refused3.4
Solar Array at Dupplin Solar 750 Metres S/O Newbigging Farm Tibbermoresolar farm97.5application submitted4.2
Binn Farm Solar Farmsolar farm39application submitted5.7
Knoweheadwind farm60refused8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4025, -3.4915).