Solar, wind and battery projects near Perth (PH2)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH2 (Perth and Kinross): 7 are waiting for a planning decision, 8 approved but not yet running, 7 operational. The largest live scheme is Brunt Hill Wind Farm & Battery Storage (130 MW wind farm, application submitted on 8 May 2024, no decision recorded; REPD status may be out of date), 5.4 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 36.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PH2
Projects of 1 MW and more (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Binn Farm Solar Farmsolar farm | solar farm | 39 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Perth and Kinross | 0.1 |
| Knoweheadwind farm | wind farm | 60 | refusedupdated Dec 2010 | Aug 2004 | refused Jul 2005 | Dec 2010 | Perth and Kinross | 3.2 |
| Pitheavliswind turbine | wind turbine | 1 | approved, not builtupdated Mar 2022 | Mar 2022 | granted Oct 2022 | Mar 2022 | Perth and Kinross | 3.6 |
| Aviva Headquarterssolar farm | solar farm | 1.8 | operationalupdated Nov 2020 | Jun 2019 | granted Jul 2019 | Nov 2020 | Perth and Kinross | 3.6 |
| Brunt Hill Wind Farm & Battery Storagewind farm | wind farm | 130 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Perth and Kinross | 5.4 |
| Brunt Hill Wind Farm & Battery Storagebattery storage | battery storage | 50 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Perth and Kinross | 5.4 |
| Old Gallows Roadbattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Feb 2024 | Apr 2021 | granted Aug 2021 | Feb 2024 | Perth and Kinross | 5.4 |
| Newhouse Farm Energy Storage Facilitybattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Jul 2022 | Jul 2022 | granted Jan 2023 | Jul 2022 | Perth and Kinross | 5.7 |
| Cordon Farmsolar farm | solar farm | 10 | permission expiredupdated Sep 2020 | Mar 2017 | granted Jul 2017 | Sep 2020 | Perth and Kinross | 6.8 |
| Cordon Farm, Abernethybattery storage | battery storage | 30 | application submittedupdated Oct 2025 | Oct 2024 | — | Oct 2025 | Perth and Kinross | 6.9 |
| Carey Solar Farmsolar farm | solar farm | 10 | permission expiredupdated Sep 2020 | Aug 2015 | granted Nov 2015 | Sep 2020 | Perth and Kinross | 7.0 |
| Taigh An Struith, Tibbermorebattery storage | battery storage | 49.9 | refusedupdated Mar 2025 | Jun 2024 | refused Mar 2025 | Mar 2025 | Perth and Kinross | 7.8 |
| Newburgh Road, Abernethybattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated May 2025 | May 2022 | granted Sep 2022 | May 2025 | Perth and Kinross | 7.8 |
| Jamesfield Organic Centrebattery storage | battery storage | 49 | operationalupdated Mar 2024 | May 2022 | granted Sep 2022 | Mar 2024 | Perth and Kinross | 7.8 |
| Jamesfield Solar Farmsolar farm | solar farm | 5 | permission expiredupdated Sep 2018 | Jun 2015 | granted Aug 2015 | Sep 2018 | Perth and Kinross | 8.0 |
| Errol Estatesolar farm | solar farm | 13 | operationalupdated Jun 2016 | Mar 2014 | granted Jun 2014 | Jun 2016 | Perth and Kinross | 8.1 |
| Jamesfield Garden Centre, Newburghbattery storage | battery storage | 49.9 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Perth and Kinross | 8.2 |
| Newburgh Road, Abernethybattery storage | battery storage | 49.9 | approved, not builtupdated Jun 2025 | Nov 2024 | granted May 2025 | Jun 2025 | Perth and Kinross | 8.4 |
| Newburgh Road, Abernethybattery storage | battery storage | 15 | approved, not built may be out of dateupdated Jul 2025 | Jan 2022 | granted Mar 2023 | Jul 2025 | Perth and Kinross | 8.7 |
| Kinnon Park Farm, Methven Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | refusedupdated Jun 2026 | Sep 2024 | refused May 2026 | Jun 2026 | Perth and Kinross | 9.1 |
| Solar Array at Dupplin Solar 750 Metres S/O Newbigging Farm Tibbermoresolar farm | solar farm | 97.5 | application submittedupdated Jun 2026 | Mar 2026 | — | Jun 2026 | Perth and Kinross | 9.1 |
| Lochelbank Wind Farmwind farm | wind farm | 51 | application withdrawnupdated Apr 2009 | — | — | Apr 2009 | Perth and Kinross | 9.3 |
| Lochelbank Wind Farm IIwind farm | wind farm | 9.6 | operationalupdated Jun 2011 | Apr 2005 | granted Aug 2007 | Jun 2011 | Perth and Kinross | 9.3 |
| Binn Eco Park Batterybattery storage | battery storage | 10 | approved, not built may be out of dateupdated Jul 2024 | May 2021 | granted Jul 2021 | Jul 2024 | Perth and Kinross | 9.9 |
| Bandirran Wind Farmwind farm | wind farm | 20.4 | application withdrawnupdated Jul 2015 | Jan 2014 | — | Jul 2015 | Perth and Kinross | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Perth Wastewater Treatment Works (Extension)solar farm | solar farm | 0.3 | operationalupdated May 2021 | May 2020 | granted Sep 2020 | May 2021 | Perth and Kinross | 1.1 |
| Perth Wastewater Treatment Works (Extension)battery storage | battery storage | — | operationalupdated Jan 2022 | May 2020 | granted Sep 2020 | Jan 2022 | Perth and Kinross | 1.1 |
| Perth Wastewater Treatment Workssolar farm | solar farm | 0.4 | operationalupdated Apr 2023 | Feb 2019 | granted Jun 2019 | Apr 2023 | Perth and Kinross | 1.2 |
| Kanthal, Ruthvenfield Roadrooftop solar | rooftop solar | — | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Perth and Kinross | 5.6 |
| Waste Water Treatment Works, Almondbank - Pumping Station & Solar Panelssolar farm | solar farm | — | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Perth and Kinross | 7.1 |
| Kinnon Park Farm, Methven Solar Farm & Battery Storagebattery storage | battery storage | — | refusedupdated Jun 2026 | Sep 2024 | refused May 2026 | Jun 2026 | Perth and Kinross | 9.8 |
Distance from the average position of the PH2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 2 | 1 | 4 | 1 | 136 |
| Rooftop solar | 1 | 1 | 0 | 0 | 0 | 0 |
| Wind farm | 5 | 1 | 0 | 1 | 1 | 130 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 1 |
| Battery storage | 13 | 3 | 6 | 2 | 2 | 354 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Forthwind | 20 | approved, not builtupdated Aug 2023 | 36.0 |
| Levenmouth demonstration turbine (Fife Energy Park) | 7 | operationalupdated Nov 2018 | 37.3 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Perth and Kinross decides solar, wind and battery applications
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
All projects in Perth and Kinross
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PH2, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.