Jamesfield Garden Centre, Newburgh (49.9 MW battery storage)

Jamesfield Garden Centre, Newburgh is a 49.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 6 February 2026, no decision recorded; the record was last updated on 2 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application submittedstatus in REPD
2 March 2026record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
6 February 2026Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
2 March 2026
Operator or applicant
Harmony Energy Limited
Planning authority
Perth and Kinross
Planning application reference
26/00067/FLM
Address (REPD)
300 Metres Nw/O Jamesfield Garden Centre, Newburgh, Cupar
Council area (by location)
Perth and Kinross
Name in REPD
Jamesfield Garden Centre, Newburgh - Battery Energy Storage
REPD reference
19734

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newburgh Road, Abernethybattery storage49.9approved, not built0.4
Newburgh Road, Abernethybattery storage15approved, not built0.5
Jamesfield Solar Farmsolar farm5permission expired0.7
Newburgh Road, Abernethybattery storage49.9approved, not built0.7
Jamesfield Organic Centrebattery storage49operational0.7
Cordon Farm, Abernethybattery storage30application submitted1.6
Cordon Farmsolar farm10permission expired1.6
Carey Solar Farmsolar farm10permission expired2.6
Errol Estatesolar farm13operational3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3417, -3.2981).