Energy Projects Near You

Jamesfield Organic Centre (49 MW battery storage)

Jamesfield Organic Centre is a 49 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2024; the record was last updated on 26 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWbattery storage
operationalstatus in REPD
26 March 2024record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
20 May 2022Application submitted
28 September 2022Planning permission granted
1 January 2023Construction started
1 February 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49 MW
Status (REPD)
operational
Record last updated
26 March 2024
Operator or applicant
Harmony Energy Storage
Planning authority
Perth and Kinross
Planning application reference
22/00832/FLM
Address (REPD)
140 Metres North East Of Jamesfield Organic Centre Newburgh, Cupar
Council area (by location)
Perth and Kinross
Time to decision
19 weeks
Name in REPD
Jamesfield Organic Centre - Battery Storage
REPD reference
10863

Earlier applications for this site

ApplicationMWSubmittedOutcome
Jamesfield Organic Centre, Phase 1 17/00951/FLL3021 July 2017replaced by a revised application
Jamesfield Organic Centre, Phase 2 18/02336/FLL199 January 2019replaced by a revised application

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newburgh Road, Abernethybattery storage49.9approved, not built<0.1
Jamesfield Solar Farmsolar farm5permission expired0.2
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted0.7
Newburgh Road, Abernethybattery storage15approved, not built0.9
Newburgh Road, Abernethybattery storage49.9approved, not built1.0
Cordon Farmsolar farm10permission expired1.5
Cordon Farm, Abernethybattery storage30application submitted1.6
Errol Estatesolar farm13operational2.6
Carey Solar Farmsolar farm10permission expired2.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3477, -3.2984).