Jamesfield Solar Farm (5 MW)

Jamesfield Solar Farm is a 5 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 14 August 2018; the record was last updated on 27 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
27 September 2018record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
17 June 2015Application submitted
14 August 2015Planning permission granted
14 August 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
27 September 2018
Operator or applicant
Green Power Consultants
Planning authority
Perth and Kinross
Planning application reference
15/00833/FLL
Site area
10.3 ha
Address (REPD)
Land 200M South E Of The Bothy, Jamesfield, Newburgh, Cupar, Fife
Council area (by location)
Perth and Kinross
Time to decision
8 weeks
REPD reference
5471

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newburgh Road, Abernethybattery storage49.9approved, not built0.2
Jamesfield Organic Centrebattery storage49operational0.2
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted0.7
Newburgh Road, Abernethybattery storage15approved, not built0.8
Newburgh Road, Abernethybattery storage49.9approved, not built1.1
Cordon Farmsolar farm10permission expired1.7
Cordon Farm, Abernethybattery storage30application submitted1.8
Errol Estatesolar farm13operational2.5
Carey Solar Farmsolar farm10permission expired2.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3474, -3.2953).