Energy Projects Near You

Newburgh Road, Abernethy (49.9 MW battery storage, 2024 application)

Newburgh Road, Abernethy is a 49.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 May 2025, not yet built; the record was last updated on 10 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
10 June 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
18 November 2024Application submitted
15 May 2025Planning permission granted
15 May 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
10 June 2025
Operator or applicant
Opdenergy
Planning authority
Perth and Kinross
Planning application reference
24/01386/FLM
Address (REPD)
200 Metres N/O Pitcurran House, Newburgh Road, Abernethy
Council area (by location)
Perth and Kinross
Time to decision
25 weeks
Name in REPD
Newburgh Road, Abernethy - Battery Energy Storage Facility
REPD reference
16286

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted0.4
Newburgh Road, Abernethybattery storage15approved, not built0.7
Newburgh Road, Abernethybattery storage49.9approved, not built1.0
Jamesfield Organic Centrebattery storage49operational1.0
Jamesfield Solar Farmsolar farm5permission expired1.1
Cordon Farm, Abernethybattery storage30application submitted1.6
Cordon Farmsolar farm10permission expired1.6
Carey Solar Farmsolar farm10permission expired2.4
Errol Estatesolar farm13operational3.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3383, -3.3004).