Newburgh Road, Abernethy (49.9 MW battery storage, 2022 application)

Newburgh Road, Abernethy is a 49.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 September 2022, not yet built; the record was last updated on 7 May 2025. REPD also records that the planning permission expired on 26 September 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
7 May 2025record last updated
Perth and Kinrosscouncil area

REPD also records that the planning permission expired on 26 September 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
11 May 2022Application submitted
26 September 2022Planning permission granted
26 September 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 May 2025
Operator or applicant
CBS Solar Assets UK Limited
Planning authority
Perth and Kinross
Planning application reference
22/00746/FLM
Address (REPD)
60 Metres North Of Abernethy Cemetery Newburgh Road Abernethy
Council area (by location)
Perth and Kinross
Time to decision
20 weeks
Name in REPD
Newburgh Road, Abernethy - Battery Storage
REPD reference
10607

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jamesfield Organic Centrebattery storage49operational<0.1
Jamesfield Solar Farmsolar farm5permission expired0.2
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted0.7
Newburgh Road, Abernethybattery storage15approved, not built0.9
Newburgh Road, Abernethybattery storage49.9approved, not built1.0
Cordon Farmsolar farm10permission expired1.5
Cordon Farm, Abernethybattery storage30application submitted1.6
Errol Estatesolar farm13operational2.6
Carey Solar Farmsolar farm10permission expired2.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3477, -3.2984).