Cordon Farm (10 MW solar farm)

Cordon Farm is a 10 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired; the record was last updated on 2 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
permission expiredstatus in REPD
2 September 2020record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
20 March 2017Application submitted
19 July 2017Planning permission granted

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
permission expired
Record last updated
2 September 2020
Operator or applicant
Elgin Energy
Planning authority
Perth and Kinross
Planning application reference
17/00487/FLL
Site area
23.0 ha
Address (REPD)
Land 400 Metres North Of Cordon Farmhouse, Abernethy
Council area (by location)
Perth and Kinross
Time to decision
17 weeks
REPD reference
6594

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cordon Farm, Abernethybattery storage30application submitted0.3
Carey Solar Farmsolar farm10permission expired1.5
Newburgh Road, Abernethybattery storage49.9approved, not built1.5
Jamesfield Organic Centrebattery storage49operational1.5
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted1.6
Newburgh Road, Abernethybattery storage49.9approved, not built1.6
Jamesfield Solar Farmsolar farm5permission expired1.7
Newburgh Road, Abernethybattery storage15approved, not built2.1
Errol Estatesolar farm13operational3.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3462, -3.3228).