Energy Projects Near You

Newburgh Road, Abernethy (15 MW battery storage)

Newburgh Road, Abernethy is a 15 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 March 2023, not yet built; the record was last updated on 25 July 2025. REPD also records that the planning permission expired on 29 March 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWbattery storage
approved, not builtmay be out of datestatus in REPD
25 July 2025record last updated
Perth and Kinrosscouncil area

REPD also records that the planning permission expired on 29 March 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
13 January 2022Application submitted
29 March 2023Planning permission granted
29 March 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
25 July 2025
Operator or applicant
Centrica Business Solutions
Planning authority
Perth and Kinross
Planning application reference
22/02217/FLL
Address (REPD)
110 Metres Ne/O Abernethy Cemetery, Abernethy Cemetery, Newburgh Road, Abernethy, Perth
Council area (by location)
Perth and Kinross
Time to decision
63 weeks
Name in REPD
Newburgh Road, Abernethy - Energy Storage
REPD reference
13111

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted0.5
Newburgh Road, Abernethybattery storage49.9approved, not built0.7
Jamesfield Solar Farmsolar farm5permission expired0.8
Newburgh Road, Abernethybattery storage49.9approved, not built0.9
Jamesfield Organic Centrebattery storage49operational0.9
Cordon Farmsolar farm10permission expired2.1
Cordon Farm, Abernethybattery storage30application submitted2.1
Carey Solar Farmsolar farm10permission expired3.0
Errol Estatesolar farm13operational3.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3408, -3.2907).