Energy Projects Near You

Brunt Hill Wind Farm & Battery Storage (130 MW)

Brunt Hill Wind Farm & Battery Storage is a 130 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 8 May 2024, no decision recorded; the record was last updated on 10 June 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

130 MWwind farm
application submittedmay be out of datestatus in REPD
10 June 2024record last updated
Perth and Kinrosscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
8 May 2024Application submitted

Project details

Technology
wind farm
Capacity
130 MW
Status (REPD)
application submitted
Record last updated
10 June 2024
Operator or applicant
E Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004654
Turbines
18
Turbine height
200 m
Address (REPD)
4.5km Nw/O Kinross, Kinross
Council area (by location)
Perth and Kinross
REPD reference
12824

The scheme also includes 50 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Old Gallows Roadbattery storage49.9approved, not built<0.1
Newhouse Farm Energy Storage Facilitybattery storage49.9approved, not built0.6
Taigh An Struith, Tibbermorebattery storage49.9refused2.3
Kinnon Park Farm, Methven Solar Farm & Battery Storagesolar farm49.9refused3.7
Solar Array at Dupplin Solar 750 Metres S/O Newbigging Farm Tibbermoresolar farm97.5application submitted4.0
Binn Farm Solar Farmsolar farm39application submitted5.4
Knoweheadwind farm60refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3969, -3.49).