Bandirran Wind Farm (20.4 MW)

Bandirran Wind Farm is a 20.4 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 23 July 2015; the record was last updated on 29 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.4 MWwind farm
application withdrawnstatus in REPD
29 July 2015record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
31 January 2014Application submitted
23 July 2015Application withdrawn

Project details

Technology
wind farm
Capacity
20.4 MW
Status (REPD)
application withdrawn
Record last updated
29 July 2015
Operator or applicant
Banks Renewables
Planning authority
Perth and Kinross
Planning application reference
14/00097/FLM
Turbines
6
Council area (by location)
Perth and Kinross
REPD reference
4567

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused4.6
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused5.2
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farm22refused7.0
Knoweheadwind farm60refused7.3
Mill Of Peattie Farm, Kinnochtry Couparbattery storage18refused7.5
Stirling Battery and Solar Energy Parksolar farm60approved, not built9.0
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farm20.5approved, not built9.0
Errol Estatesolar farm13operational9.3
Coupar Angus Substation, Pleasance Road Solar Farmsolar farm49.9refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4509, -3.2886).