Energy Projects Near You

Milton Of Collace, Burrelton Solar Farm (49.9 MW, REPD 16122)

Milton Of Collace, Burrelton Solar Farm is a 49.9 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 11 June 2025; the record was last updated on 1 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
1 July 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
13 March 2024Application submitted
11 June 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
1 July 2025
Operator or applicant
Solar 2 Limited
Planning authority
Perth and Kinross
Planning application reference
24/00070/FLM
Site area
100.0 ha
Address (REPD)
Milton Of Collace, Burrelton, Blairgowrie
Council area (by location)
Perth and Kinross
Time to decision
65 weeks
Name in REPD
Milton Of Collace, Burrelton - Solar Farm
REPD reference
16122

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused0.7
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farm22refused4.0
Mill Of Peattie Farm, Kinnochtry Couparbattery storage18refused4.3
Bandirran Wind Farmwind farm20.4application withdrawn4.6
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farm20.5approved, not built4.8
Stirling Battery and Solar Energy Parksolar farm60approved, not built4.8
Coupar Angus Substation, Pleasance Road Solar Farmsolar farm49.9refused5.8
Pleasance Road Battery Energy Facilitybattery storage49.9operational5.9
Coupar Angus, Pleasance Road Battery Energy Facilitybattery storage49.9approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4898, -3.3143).