Mains Of Keithick Farm, Keithick Battery Storage & Solar Farm (20.5 MW)
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farm is a 20.5 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 March 2025, not yet built; the record was last updated on 19 February 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.
Planning timeline
| Date | Stage |
|---|---|
| 22 July 2022 | Application submitted |
| 13 March 2025 | Section 36 consent granted (Scottish Ministers) |
Project details
- Technology
- solar farm
- Capacity
- 20.5 MW
- Status (REPD)
- approved, not built
- Record last updated
- 19 February 2026
- Operator or applicant
- EcoDev Group Limited
- Planning authority
- Scottish Government (S36)
- Planning application reference
- ECU00004521
- Site area
- 54.0 ha
- Address (REPD)
- Mains Of Keithick Farm, Keithick, Blairgowrie
- Council area (by location)
- Perth and Kinross
- Time to decision
- 138 weeks
- Contracts for Difference
- AR7a
- Name in REPD
- Mains Of Keithick Farm, Keithick - Battery Storage & Solar Farm
- REPD reference
- 11622
The scheme also includes 16 MW of battery storage, recorded separately in REPD (approved, not built).
Who decides
As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Stirling Battery and Solar Energy Park | solar farm | 60 | approved, not built | <0.1 |
| Pleasance Road Battery Energy Facility | battery storage | 49.9 | operational | 1.6 |
| Coupar Angus, Pleasance Road Battery Energy Facility | battery storage | 49.9 | approved, not built | 1.8 |
| Coupar Angus Substation, Pleasance Road Solar Farm | solar farm | 49.9 | refused | 1.9 |
| Mill Of Peattie Farm, Kinnochtry Coupar | battery storage | 18 | refused | 2.7 |
| Mill Of Peattie Farm, Kinnochtry Coupar Solar Farm | solar farm | 22 | refused | 3.0 |
| Hallyburton | battery storage | 100 | approved, not built | 3.6 |
| Milton Of Collace, Burrelton Solar Farm | solar farm | 49.9 | refused | 4.5 |
| Milton Of Collace, Burrelton Solar Farm | solar farm | 49.9 | refused | 4.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5321, -3.2971).