Energy Projects Near You

Mill Of Peattie Farm, Kinnochtry Coupar (18 MW battery storage)

Mill Of Peattie Farm, Kinnochtry Coupar is an 18 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 July 2025; the record was last updated on 25 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWbattery storage
refusedstatus in REPD
25 July 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
4 February 2025Application submitted
9 July 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
18 MW
Status (REPD)
refused
Record last updated
25 July 2025
Operator or applicant
Greentech
Planning authority
Perth and Kinross
Planning application reference
25/00104/FLM
Address (REPD)
Mill Of Peattie Farm, Kinnochtry Coupar, Angus Blairgowrie, Blairgowrie, Tayside
Council area (by location)
Perth and Kinross
Time to decision
22 weeks
Name in REPD
Mill Of Peattie Farm, Kinnochtry Coupar - Battery Storage
REPD reference
15690

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farm22refused0.5
Coupar Angus Substation, Pleasance Road Solar Farmsolar farm49.9refused2.1
Pleasance Road Battery Energy Facilitybattery storage49.9operational2.4
Stirling Battery and Solar Energy Parksolar farm60approved, not built2.7
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farm20.5approved, not built2.7
Hallyburtonbattery storage100approved, not built2.8
Coupar Angus, Pleasance Road Battery Energy Facilitybattery storage49.9approved, not built2.9
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused4.3
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5165, -3.2636).