Energy Projects Near You

Hallyburton (100 MW battery storage)

Hallyburton is a 100 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 October 2025, not yet built; the record was last updated on 16 December 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
16 December 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
6 December 2024Application submitted
2 October 2025Section 36 consent granted (Scottish Ministers)
2 October 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
16 December 2025
Operator or applicant
Balance Power Projects Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004931
Address (REPD)
Hallyburton, Kettins, Blairgowrie
Council area (by location)
Perth and Kinross
Time to decision
43 weeks
Name in REPD
Hallyburton - Battery Storage
REPD reference
14990

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Coupar Angus Substation, Pleasance Road Solar Farmsolar farm49.9refused1.7
Pleasance Road Battery Energy Facilitybattery storage49.9operational2.0
Coupar Angus, Pleasance Road Battery Energy Facilitybattery storage49.9approved, not built2.1
Mill Of Peattie Farm, Kinnochtry Couparbattery storage18refused2.8
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farm22refused3.2
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farm20.5approved, not built3.6
Stirling Battery and Solar Energy Parksolar farm60approved, not built3.6
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused7.1
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5384, -3.2402).