Coupar Angus, Pleasance Road Battery Energy Facility (49.9 MW)

Coupar Angus, Pleasance Road Battery Energy Facility is a 49.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 September 2024, not yet built; the record was last updated on 24 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
24 September 2024record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
13 March 2024Application submitted
11 September 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
24 September 2024
Operator or applicant
Gresham House Asset Management Limited
Planning authority
Perth and Kinross
Planning application reference
24/00200/FLM
Address (REPD)
130 Metres South East Of Coupar Angus Substation Pleasance Road
Council area (by location)
Perth and Kinross
Time to decision
26 weeks
Name in REPD
Coupar Angus, Pleasance Road - Battery Energy Facility
REPD reference
16137

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pleasance Road Battery Energy Facilitybattery storage49.9operational0.5
Coupar Angus Substation, Pleasance Road Solar Farmsolar farm49.9refused0.9
Stirling Battery and Solar Energy Parksolar farm60approved, not built1.8
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farm20.5approved, not built1.8
Hallyburtonbattery storage100approved, not built2.1
Mill Of Peattie Farm, Kinnochtry Couparbattery storage18refused2.9
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farm22refused3.4
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused6.1
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5421, -3.2733).