Energy Projects Near You

Coupar Angus Substation, Pleasance Road Solar Farm (49.9 MW)

Coupar Angus Substation, Pleasance Road Solar Farm is a 49.9 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 14 December 2023; the record was last updated on 4 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
4 January 2024record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
18 August 2023Application submitted
14 December 2023Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
4 January 2024
Operator or applicant
Coupar Two Limited
Planning authority
Perth and Kinross
Planning application reference
23/01294/FLM
Site area
90.6 ha
Address (REPD)
Se/O Coupar Angus Substation, Pleasance Road, Coupar Angus, Blairgowrie
Council area (by location)
Perth and Kinross
Time to decision
17 weeks
Name in REPD
Coupar Angus Substation, Pleasance Road - Solar Farm
REPD reference
14792

Earlier applications for this site

ApplicationMWSubmittedOutcome
Pleasance Road, Coupar 22/01285/FLM49.99 August 2022refused 23 February 2023

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pleasance Road Battery Energy Facilitybattery storage49.9operational0.5
Coupar Angus, Pleasance Road Battery Energy Facilitybattery storage49.9approved, not built0.9
Hallyburtonbattery storage100approved, not built1.7
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farm20.5approved, not built1.9
Stirling Battery and Solar Energy Parksolar farm60approved, not built1.9
Mill Of Peattie Farm, Kinnochtry Couparbattery storage18refused2.1
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farm22refused2.5
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused5.7
Milton Of Collace, Burrelton Solar Farmsolar farm49.9refused5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5349, -3.2672).