Forthwind offshore wind farm

Forthwind is a 20 MW offshore wind farm with 1 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 March 2023, not yet built; the record was last updated on 2 August 2023. Its REPD grid reference is 3 km from the nearest postcode on land (KY8 1AQ, Fife). As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWoffshore wind farm
approved, not builtstatus in REPD
2 August 2023record last updated
3 km from land (Fife)REPD location

Consent timeline

DateStage
29 April 2022Application submitted
15 March 2023Marine licence and Section 36 consent granted (Scottish Ministers)
31 October 2049Permission due to expire (unless work starts)

Project details

Technology
offshore wind farm
Capacity
20 MW
Turbines
1
Turbine capacity
20 MW
Turbine height
280 m
Status (REPD)
approved, not built
Record last updated
2 August 2023
Operator or applicant
Cierco
Consenting authority (REPD)
Marine Scotland
Application reference
MS-00009834
Nearest postcode on land
KY8 1AQ (Fife), 2.7 km from the REPD grid reference
Time to decision
46 weeks
REPD reference
14484

Earlier applications

ApplicationMWSubmittedOutcome
Forthwind—6 July 2015replaced by a revised application

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Postcode districts within 40 km

Districtkm
Leven (KY8)4.8
Kirkcaldy (KY1)9.1
Glenrothes (KY7)11.0
Elie (KY9)11.8
Kirkcaldy (KY2)12.1
Glenrothes (KY6)13.4
Cupar (KY15)16.4
Gullane (EH31)17.0
Burntisland (KY3)17.7
Lochgelly (KY5)18.4
Anstruther (KY10)20.2
North Berwick (EH39)20.3

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Levenmouth demonstration turbine (Fife Energy Park)7operational2.5

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (56.1552, -2.9974).