Energy Projects Near You

Solar, wind and battery projects near Gullane (EH31)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH31 (East Lothian): 1 is waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Haddington Sewage Works, Haddington East (0.2 MW rooftop solar, application submitted on 2 April 2026, no decision recorded), 9.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Levenmouth demonstration turbine (Fife Energy Park) (7 MW, operational), 16.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
1awaiting a decision
1approved, not running
0operational

Projects within 10 km of EH31

Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Haddington Sewage Works, Haddington Eastrooftop solarrooftop solar0.2application submittedupdated May 2026Apr 2026—May 2026East Lothian9.5
Seton Sands, Holiday Villagerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jun 2023Jul 2023East Lothian9.6

Distance from the average position of the EH31 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar211000.4

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201816.1
Forthwind20approved, not builtupdated Aug 202317.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lothian decides solar, wind and battery applications

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in East Lothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH31, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.