Energy Projects Near You

Solar, wind and battery projects near Tranent (EH33)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH33 (East Lothian): 7 approved but not yet running. The largest live scheme is Cockenzie Battery Storage System - Site A (240 MW battery storage, approved on 23 July 2025, not yet built), 3.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 24.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
7approved, not running
0operational

Projects within 10 km of EH33

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dolphingstone Farmbattery storagebattery storage63approved, not builtupdated Oct 2025Nov 2023granted Jul 2025Oct 2025East Lothian2.8
Cockenzie Battery Storage System - Site Abattery storagebattery storage240approved, not builtupdated Oct 2025Aug 2023granted Jul 2025Oct 2025East Lothian3.1
Cockenzie Battery Storage System - Site Bbattery storagebattery storage102approved, not builtupdated Oct 2025Nov 2024granted Jul 2025Oct 2025East Lothian3.1
Smeaton Battery Energy Storage Systembattery storagebattery storage228approved, not builtupdated Oct 2024Mar 2023granted Aug 2024Oct 2024East Lothian6.4
Salters Battery Energy Storage Systembattery storagebattery storage200approved, not builtupdated Jul 2025Aug 2024granted May 2025Jul 2025Midlothian8.4
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Meadow Stores, Ormistonsolar farmsolar farm0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024East Lothian2.4
Seton Sands, Holiday Villagerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jun 2023Jul 2023East Lothian3.6

Distance from the average position of the EH33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Rooftop solar101000.2
Battery storage50500833

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202324.0
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201824.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lothian decides solar, wind and battery applications

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in East Lothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH33, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.