Energy Projects Near You

Solar, wind and battery projects near Ormiston (EH35)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH35 (East Lothian): 11 approved but not yet running, 1 operational. The largest live scheme is Cockenzie Battery Storage System - Site A (240 MW battery storage, approved on 23 July 2025, not yet built), 6.4 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 27.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
0awaiting a decision
11approved, not running
1operational

Projects within 10 km of EH35

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dolphingstone Farmbattery storagebattery storage63approved, not builtupdated Oct 2025Nov 2023granted Jul 2025Oct 2025East Lothian4.7
Smeaton Battery Energy Storage Systembattery storagebattery storage228approved, not builtupdated Oct 2024Mar 2023granted Aug 2024Oct 2024East Lothian5.7
Cockenzie Battery Storage System - Site Abattery storagebattery storage240approved, not builtupdated Oct 2025Aug 2023granted Jul 2025Oct 2025East Lothian6.4
Cockenzie Battery Storage System - Site Bbattery storagebattery storage102approved, not builtupdated Oct 2025Nov 2024granted Jul 2025Oct 2025East Lothian6.4
Salters Battery Energy Storage Systembattery storagebattery storage200approved, not builtupdated Jul 2025Aug 2024granted May 2025Jul 2025Midlothian7.0
Gilston Wind Farm (Lothian)wind farmwind farm18.5refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013Midlothian10.0
Gilston Wind Farm (Borders)wind farmwind farm14.4refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013Midlothian10.0
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Meadow Stores, Ormistonsolar farmsolar farm0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024East Lothian1.2
Seton Sands, Holiday Villagerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jun 2023Jul 2023East Lothian6.9
Howden Farmrooftop solarrooftop solar0.2operationalupdated Sep 2023Mar 2020granted Apr 2020Sep 2023East Lothian8.7
Edinburgh College, Dalhousie Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023Midlothian9.0
Howden Farm Turbine, Giffordwind turbinewind turbine0.9approved, not builtupdated May 2026Oct 2024granted Sep 2025May 2026East Lothian9.2
Butlerfield Industrial Estaterooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Midlothian9.5
Old Dalkeith Road, Danderhallrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Midlothian9.6

Distance from the average position of the EH35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Rooftop solar504100.9
Wind farm200020
Wind turbine101000.9
Battery storage50500833

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202327.4
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201827.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lothian decides solar, wind and battery applications

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in East Lothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH35, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.