Cockenzie Battery Storage System - Site B (102 MW)

Cockenzie Battery Storage System - Site B is a 102 MW battery storage project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 July 2025, not yet built; the record was last updated on 1 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

102 MWbattery storage
approved, not builtstatus in REPD
1 October 2025record last updated
East Lothiancouncil area

Planning timeline

DateStage
12 November 2024Application submitted
23 July 2025Section 36 consent granted (Scottish Ministers)
23 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
102 MW
Status (REPD)
approved, not built
Record last updated
1 October 2025
Operator or applicant
Gresham House
Planning authority
Scottish Government (S36)
Planning application reference
ECU00006022
Address (REPD)
W/O Avenue Road, SE/O Edinburgh Road, S/O Ingis Farm, Cockenzie
Council area (by location)
East Lothian
Time to decision
36 weeks
REPD reference
17556

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cockenzie Battery Storage System - Site Abattery storage240approved, not built<0.1
Dolphingstone Farmbattery storage63approved, not built3.1
Smeaton Battery Energy Storage Systembattery storage228approved, not built7.6
Salters Battery Energy Storage Systembattery storage200approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9675, -2.962).