Energy Projects Near You

Smeaton Battery Energy Storage System (228 MW)

Smeaton Battery Energy Storage System is a 228 MW battery storage project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 August 2024, not yet built; the record was last updated on 7 October 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

228 MWbattery storage
approved, not builtstatus in REPD
7 October 2024record last updated
East Lothiancouncil area

Planning timeline

DateStage
21 March 2023Application submitted
29 August 2024Section 36 consent granted (Scottish Ministers)
29 August 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
228 MW
Status (REPD)
approved, not built
Record last updated
7 October 2024
Operator or applicant
Kona Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004783
Address (REPD)
Smeaton, Whitecraig, East Lothian,
Council area (by location)
East Lothian
Time to decision
75 weeks
REPD reference
13627

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Salters Battery Energy Storage Systembattery storage200approved, not built2.3
Dolphingstone Farmbattery storage63approved, not built4.5
Cockenzie Battery Storage System - Site Bbattery storage102approved, not built7.6
Cockenzie Battery Storage System - Site Abattery storage240approved, not built7.6
Existing Kaimes Substation, Old Burdiehouse Roadbattery storage49.9application submitted8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9132, -3.0361).