Energy Projects Near You

Existing Kaimes Substation, Old Burdiehouse Road (49.9 MW battery storage)

Existing Kaimes Substation, Old Burdiehouse Road is a 49.9 MW battery storage project in City of Edinburgh, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 26 March 2024, no decision recorded; the record was last updated on 9 April 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application submittedmay be out of datestatus in REPD
9 April 2024record last updated
City of Edinburghcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
26 March 2024Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
9 April 2024
Operator or applicant
Kaimes Renewable Energy Park
Planning authority
City of Edinburgh
Planning application reference
24/01489/FUL
Address (REPD)
West Of Existing Kaimes Substation Old Burdiehouse Road
Council area (by location)
City of Edinburgh
Name in REPD
Existing Kaimes Substation, Old Burdiehouse Road - Battery Storage
REPD reference
13809

Who decides

ApplicationsCity of EdinburghUK
Decided applications (solar, wind, battery)1610,236
Refused0 (0%)19%
Solar refused0 of 1612%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Salters Battery Energy Storage Systembattery storage200approved, not built6.8
Smeaton Battery Energy Storage Systembattery storage228approved, not built8.1
Riccarton Mains Roadbattery storage150application submitted9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.895, -3.1622).