Energy Projects Near You

Salters Battery Energy Storage System (200 MW)

Salters Battery Energy Storage System is a 200 MW battery storage project in Midlothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 May 2025, not yet built; the record was last updated on 1 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
1 July 2025record last updated
Midlothiancouncil area

Planning timeline

DateStage
21 August 2024Application submitted
12 May 2025Section 36 consent granted (Scottish Ministers)
12 May 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
1 July 2025
Operator or applicant
Buccleuch Group
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004962
Address (REPD)
South of A68 and approximately c80m North of Dalkeith High School
Council area (by location)
Midlothian
Time to decision
38 weeks
REPD reference
15173

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Smeaton Battery Energy Storage Systembattery storage228approved, not built2.3
Dolphingstone Farmbattery storage63approved, not built6.7
Existing Kaimes Substation, Old Burdiehouse Roadbattery storage49.9application submitted6.8
Cockenzie Battery Storage System - Site Abattery storage240approved, not built9.8
Cockenzie Battery Storage System - Site Bbattery storage102approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8951, -3.0529).