Energy Projects Near You

Solar, wind and battery projects near Gorebridge (EH23)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH23 (Midlothian): 5 are waiting for a planning decision, 7 approved but not yet running, 1 operational. The largest live scheme is Smeaton Battery Energy Storage System (228 MW battery storage, approved on 29 August 2024, not yet built), 8.2 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 35.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
5awaiting a decision
7approved, not running
1operational

Projects within 10 km of EH23

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Salters Battery Energy Storage Systembattery storagebattery storage200approved, not builtupdated Jul 2025Aug 2024granted May 2025Jul 2025Midlothian6.2
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farmwind farm108application submitted may be out of dateupdated Feb 2023Nov 2023—Feb 2023Midlothian6.8
Penicuik, Moorfoot Hills - Torfichen Wind Farmbattery storagebattery storage50application submitted may be out of dateupdated Mar 2023Nov 2023—Mar 2023Midlothian6.8
Falahillwind farmwind farm6.7refusedupdated May 2006Dec 2004refused May 2006May 2006Scottish Borders7.6
Smeaton Battery Energy Storage Systembattery storagebattery storage228approved, not builtupdated Oct 2024Mar 2023granted Aug 2024Oct 2024East Lothian8.2
Carcant Windfarmwind farmwind farm6operationalupdated Jan 2015Oct 2005granted Sep 2006Jan 2015Scottish Borders8.6
Mount Lothian Wind Farmwind farmwind farm20.7refused on appealupdated Nov 2015Jan 2014refused Nov 2015Nov 2015Midlothian9.1
Existing Kaimes Substation, Old Burdiehouse Roadbattery storagebattery storage49.9application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024City of Edinburgh9.3
Easter Bushsolar farmsolar farm3under constructionupdated Sep 2020Jan 2019granted Oct 2021Sep 2020Midlothian9.6
Wull Muir Wind Farmwind farmwind farm36refusedupdated Aug 2024Dec 2022refused Jul 2024Aug 2024Scottish Borders9.8
Gilston Wind Farm (Lothian)wind farmwind farm18.5refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013Midlothian9.9
Gilston Wind Farm (Borders)wind farmwind farm14.4refused on appealupdated Sep 2013Dec 2011refused Dec 2012Sep 2013Midlothian9.9
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Butlerfield Industrial Estaterooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Midlothian2.8
Edinburgh College, Dalhousie Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023Midlothian5.1
Hawthornden Castlesolar farmsolar farm0.2approved, not builtupdated Jun 2024Oct 2023granted Apr 2024Jun 2024Midlothian6.2
Wull Muir Wind Farmbattery storagebattery storage—refusedupdated Aug 2024Dec 2022refused Jul 2024Aug 2024Scottish Borders7.9
Old Dalkeith Road, Danderhallrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Midlothian8.0
Sainsburys Supermarket, Straiton Mainsrooftop solarrooftop solar0.6application submitted may be out of dateupdated Aug 2023Aug 2023—Aug 2023Midlothian8.6
James Hamilton Way Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Mar 2022Feb 2022—Mar 2022Midlothian9.1

Distance from the average position of the EH23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm312003.2
Rooftop solar413001.3
Wind farm71015108
Battery storage52201528

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202335.3
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201836.2

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Midlothian decides solar, wind and battery applications

ApplicationsMidlothianUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused0 of 712%
Onshore wind refused4 of 445%
Median time from submission to decision45.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Midlothian

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH23, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.