Wull Muir Wind Farm (36 MW)

Wull Muir Wind Farm is a 36 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 July 2024; the record was last updated on 19 August 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
refusedstatus in REPD
19 August 2024record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
16 December 2022Application submitted
8 July 2024Refused by the planning authority

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
refused
Record last updated
19 August 2024
Operator or applicant
Energiekontor UK Limited
Planning authority
Scottish Borders
Planning application reference
22/01960/FUL
Turbines
8
Turbine height
150 m
Address (REPD)
North Of Carcant Lodge Wull Muir Wind Farm Heriot
Council area (by location)
Scottish Borders
Time to decision
81 weeks
REPD reference
12353

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Falahillwind farm6.7refused2.7
Carcant Windfarmwind farm6operational3.1
Wind Farm at Greystone Knowe Wind Farmwind farm75application submitted3.5
Toddleburnwind farm27.6operational5.7
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted5.8
Gilston Hill Wind Farmwind farm21refused on appeal6.6
Rowantree Wind Farmwind farm69refused8.1
Gilston Wind Farm (Borders)wind farm14.4refused on appeal8.1
Gilston Wind Farm (Lothian)wind farm18.5refused on appeal8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7646, -2.9675).