Energy Projects Near You

Carcant Windfarm (6 MW)

Carcant Windfarm is a 6 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 November 2010; the record was last updated on 5 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
5 January 2015record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
10 October 2005Application submitted
15 September 2006Planning permission granted
1 April 2010Construction started
2 November 2010Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
5 January 2015
Operator or applicant
Greencoat UK Wind
Planning authority
Scottish Borders
Planning application reference
05/01884/FUL
Turbines
3
Address (REPD)
Innerleithen
Council area (by location)
Scottish Borders
Time to decision
49 weeks
REPD reference
3214

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted2.9
Wull Muir Wind Farmwind farm36refused3.1
Falahillwind farm6.7refused3.9
Wind Farm at Greystone Knowe Wind Farmwind farm75application submitted4.7
Bowbeat Emly Bank / Rough Sidewind farm31.2operational7.4
Toddleburnwind farm27.6operational8.8
Gilston Hill Wind Farmwind farm21refused on appeal9.1
Mount Lothian Wind Farmwind farm20.7refused on appeal9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7648, -3.0176).