Energy Projects Near You

Bowbeat Emly Bank / Rough Side (31.2 MW wind farm)

Bowbeat Emly Bank / Rough Side is a 31.2 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 September 2002; the record was last updated on 10 February 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31.2 MWwind farm
operationalstatus in REPD
10 February 2011record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
23 March 2000Application submitted
14 August 2000Planning permission granted
15 September 2002Operational

Project details

Technology
wind farm
Capacity
31.2 MW
Status (REPD)
operational
Record last updated
10 February 2011
Operator or applicant
PowerGen and Natural Power
Planning authority
Scottish Borders
Planning application reference
00/00371/FUL
Turbines
24
Turbine height
80 m
Address (REPD)
Roughside Moss, Peebles
Council area (by location)
Scottish Borders
Time to decision
21 weeks
REPD reference
3299

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Scawd Law Wind Farmwind farm48application submitted6.9
Wind Farm at Greystone Knowe Wind Farmwind farm75application submitted7.0
Carcant Windfarmwind farm6operational7.4
Penicuik, Moorfoot Hills - Torfichen Wind Farmwind farm108application submitted8.2
Wull Muir Wind Farmwind farm36refused9.2
Wind Farm at Leithenwater Wind Energy Hubwind farm85.8application submitted9.5
Wind Farm at Leithenwater Wind Energy Hubbattery storage10application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7046, -3.0677).