Energy Projects Near You

Wind Farm at Leithenwater Wind Energy Hub (85.8 MW)

Wind Farm at Leithenwater Wind Energy Hub is an 85.8 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 4 April 2024, no decision recorded; the record was last updated on 14 June 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

85.8 MWwind farm
application submittedmay be out of datestatus in REPD
14 June 2024record last updated
Scottish Borderscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
4 April 2024Application submitted

Project details

Technology
wind farm
Capacity
85.8 MW
Status (REPD)
application submitted
Record last updated
14 June 2024
Operator or applicant
Belltown Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004619
Turbines
13
Turbine height
200 m
Address (REPD)
Leithenwater Wind Energy Hub, 4.5km NE/O Peebles, Peebles
Council area (by location)
Scottish Borders
Name in REPD
Leithenwater Wind Energy Hub - Wind Farm
REPD reference
12283

The scheme also includes 10 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilrubie Wind Farmwind farm21appeal withdrawn8.4
Cloich Forest Wind Farmwind farm63application submitted8.8
Bowbeat Emly Bank / Rough Sidewind farm31.2operational9.5
Hag Lawwind farm20refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.652, -3.1874).