Energy Projects Near You

Solar, wind and battery projects near Peebles (EH45)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH45 (Scottish Borders): 4 are waiting for a planning decision, 1 operational. The largest live scheme is Wind Farm at Leithenwater Wind Energy Hub (85.8 MW wind farm, application submitted on 4 April 2024, no decision recorded; REPD status may be out of date), 0.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
4awaiting a decision
0approved, not running
1operational

Projects within 10 km of EH45

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wind Farm at Leithenwater Wind Energy Hubwind farmwind farm85.8application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders0.3
Wind Farm at Leithenwater Wind Energy Hubbattery storagebattery storage10application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Scottish Borders0.3
Kilrubie Wind Farmwind farmwind farm21appeal withdrawnupdated Nov 2016Jul 2015—Nov 2016Scottish Borders8.1
Blinkbonnywind farmwind farm4.6application withdrawnupdated Oct 2013Jun 2013—Oct 2013Scottish Borders8.3
Cloich Forest Wind Farmwind farmwind farm63application submitted may be out of dateupdated Jul 2021Jun 2021—Jul 2021Scottish Borders8.5
Hag Lawwind farmwind farm20refused on appealupdated Aug 2016Jul 2014refused Feb 2015Aug 2016Scottish Borders9.4
Bowbeat Emly Bank / Rough Sidewind farmwind farm31.2operationalupdated Feb 2011Mar 2000granted Aug 2000Feb 2011Scottish Borders9.5
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bonnycraigs Water Treatment Works, Bonnington Roadsolar farmsolar farm0.3application submittedupdated May 2026Apr 2026—May 2026Scottish Borders1.4

Distance from the average position of the EH45 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110000.3
Wind farm62011149
Battery storage1100010

MW in pipeline: pending, approved and under-construction capacity.

How Scottish Borders decides solar, wind and battery applications

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

All projects in Scottish Borders

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH45, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.